471cf6fb3c Project tracker seeded from the Mega Infrastructure Candy barchart
App for the Mega Infrastructure AI Integration programme (A000) and Mega
Plant (B110). 100 activities across 2 programmes, 06 Oct 2026 - 31 Aug 2027,
parsed from the client PDF and frozen as an immutable baseline.

Views: Dashboard, Timeline (month grid + week grid matching the PDF's
Friday-anchored week numbering), Todo list, WBS, Data.

Notes on the source data:
- Hierarchy is derived from the PDF's indentation, not the activity code.
  Codes do not sort structurally (A490 sits under Workforce, A510 under
  Financials), so a code-ordered import would produce a wrong tree.
- The schedule is built from the dates, not the PDF's "Durn" column, which
  disagrees with its own dates for 13 of the 100 activities.
- Spec issues found in the PDF are surfaced in-app under Data: 2 unresolved
  "?" placeholders, 6 activities sharing one stretched 6-week window while
  declared 15 days, 13 duration mismatches, 17 spelling corrections
  (original wording preserved and viewable).

Progress (status, % complete, note) is stored behind a pluggable adapter so
the site can be static today and point at a shared JSON store later without
touching the UI.