Mega-Tracker/package.json
Dave 471cf6fb3c Project tracker seeded from the Mega Infrastructure Candy barchart
App for the Mega Infrastructure AI Integration programme (A000) and Mega
Plant (B110). 100 activities across 2 programmes, 06 Oct 2026 - 31 Aug 2027,
parsed from the client PDF and frozen as an immutable baseline.

Views: Dashboard, Timeline (month grid + week grid matching the PDF's
Friday-anchored week numbering), Todo list, WBS, Data.

Notes on the source data:
- Hierarchy is derived from the PDF's indentation, not the activity code.
  Codes do not sort structurally (A490 sits under Workforce, A510 under
  Financials), so a code-ordered import would produce a wrong tree.
- The schedule is built from the dates, not the PDF's "Durn" column, which
  disagrees with its own dates for 13 of the 100 activities.
- Spec issues found in the PDF are surfaced in-app under Data: 2 unresolved
  "?" placeholders, 6 activities sharing one stretched 6-week window while
  declared 15 days, 13 duration mismatches, 17 spelling corrections
  (original wording preserved and viewable).

Progress (status, % complete, note) is stored behind a pluggable adapter so
the site can be static today and point at a shared JSON store later without
touching the UI.
2026-10-01 08:48:51 +02:00

23 lines
496 B
JSON

{
"name": "mega-project-tracker",
"private": true,
"version": "1.0.0",
"type": "module",
"scripts": {
"dev": "vite",
"build": "tsc -b && vite build",
"preview": "vite preview",
"typecheck": "tsc --noEmit"
},
"dependencies": {
"react": "^18.3.1",
"react-dom": "^18.3.1"
},
"devDependencies": {
"@types/react": "^18.3.12",
"@types/react-dom": "^18.3.1",
"@vitejs/plugin-react": "^4.3.4",
"typescript": "^5.6.3",
"vite": "^5.4.11"
}
}